
AI-generated scene with Bid Sharp banner
Electrical estimating starts with a careful takeoff: counting devices and fixtures, measuring conduit and wire runs, listing panels and gear, and then pricing material and labor. Because electrical drawings show symbols, schedules and diagrams instead of finished dimensions, a lot depends on how the estimator reads and organizes them. This guide walks through the takeoff step by step and points out where electrical bids most often go wrong.
Where electrical work sits in the documents
In the CSI MasterFormat, electrical is Division 26. Related work sits in Division 27 (Communications) and Division 28 (Electronic Safety and Security, such as fire alarm and access control), and some projects keep lighting controls or low-voltage items in separate sections. Read the Division 26 sections, the electrical drawings (usually sheets prefixed E), the symbol legend and the electrical schedules together. Coordinate with the architectural reflected ceiling plans and the mechanical drawings for equipment that needs power.
Step 1: Gather and organize the documents
- Electrical drawings: power plans, lighting plans, one-line diagram, panel schedules, fixture schedule, details and riser diagrams.
- Specifications: wiring methods, equipment, fixtures, lighting controls, testing and closeout requirements.
- Addenda, which often revise fixture types and equipment.
Step 2: Count the devices and fixtures
Go floor by floor and area by area, counting each symbol type: receptacles, switches, occupancy sensors, light fixtures by type letter, exit signs, emergency fixtures, data and communication outlets and equipment connections. Use the legend to avoid miscounting similar symbols, and mark each counted item on the plan so a reviewer can verify it. Check the fixture schedule for the exact catalog types and any alternates.
Step 3: Measure the conduit and wire runs
Runs are usually not drawn to scale in detail, so estimators measure from panel to device along the likely path, add vertical drops and rises from ceiling or floor heights, and add an allowance for offsets and pull boxes. Group runs by conduit type and size (for example EMT, rigid or PVC) and by conductor size. Wire quantity follows the circuit: the length of the run times the number of conductors, with extra for terminations. Branch circuits, feeders and homeruns should be listed separately because their materials and labor differ.
Step 4: Panels, gear and equipment
List switchgear, panelboards, transformers, disconnects, starters, generators and transfer switches from the one-line diagram and schedules. Include breakers by frame and rating, mounting hardware, pads or supports, and any required labeling. Equipment that is furnished by others but connected by the electrical contractor needs a connection allowance.
Step 5: Supports, boxes and small materials
Boxes, covers, fittings, straps, hangers, anchors, fire-stopping and identification add up. Many estimators price these as a percentage of the main material or as assemblies, for example a standard device assembly that includes the box, cover plate, device and typical wire. Whatever method you use, apply it consistently and review it against past jobs.
Step 6: Labor
Labor is calculated from quantities and unit labor values, adjusted for the project. Published labor-unit manuals, such as those from the National Electrical Contractors Association, give a starting point, but your own records are better. Adjust for working height, access, congestion, shift restrictions, the experience of the crew and the local wage rates, including prevailing wage if the job requires it. Add time for layout, testing, commissioning, as-builts and cleanup.
Step 7: Subcontracts, equipment and general conditions
Include specialty subcontractors such as fire alarm, low-voltage cabling, lighting controls, excavation for underground conduit and testing agencies, plus lifts, tools and temporary power. Then add supervision, project management, insurance, bonds, overhead and profit according to your own practice and the bid form.
Common electrical estimating mistakes
- Counting from the plan only and missing items that appear in the specifications or schedules.
- Using a fixture type that was replaced by an addendum.
- Forgetting equipment connections for mechanical, kitchen or owner-furnished items.
- Underestimating wire quantities on long feeders and homeruns, or forgetting extra for terminations.
- Not allowing for underground conduit, trenching, concrete encasement and restoration when the site work is in your scope.
- Omitting temporary power and lighting or testing and commissioning.
- Missing code or wage requirements. Always confirm the code edition and local requirements with the authority having jurisdiction, and the wage rates with the awarding agency.
A small worked example: one branch circuit
This example only illustrates the arithmetic; real jobs use the actual routing and the project's wiring method. A receptacle circuit leaves a panel, runs 60 feet along the corridor to the first device, then continues to four more devices spaced 15 feet apart. The horizontal run is 60 + (4 x 15) = 120 feet. Add 10 feet of vertical conduit at the panel and a 4-foot drop to each of the five devices: 10 + (5 x 4) = 30 feet. Total conduit is about 150 feet. With three conductors (hot, neutral, ground), wire is 150 x 3 = 450 feet. Add an allowance for terminations and waste, for example 10 percent, and the quantity to price is about 495 feet. The estimator then adds the boxes, covers, devices, connectors, supports and fire-stopping that belong to those five outlets.
Reading electrical symbols and schedules
Every drawing set has its own legend, so never rely on memory. Check whether a symbol means a standard or a special-purpose device (for example a ground-fault or isolated-ground receptacle), and cross-check each fixture type letter against the fixture schedule. Panel schedules list the circuits, breaker sizes and loads, which also tells you which feeders and homeruns exist. Note keynotes and general notes on each sheet: they often add work such as additional boxes, firestopping or coordination requirements that no symbol shows.
Prevailing wage and union work
On public projects and some private ones, electrical labor must be paid prevailing wage, which includes fringe benefits and requires certified payroll reports. These rates differ by county and classification and change over time. Use the wage determination in the solicitation, add payroll reporting time, and confirm current requirements with the awarding agency. On open-shop private work, use your own market rates.
What a good electrical takeoff looks like
It lists counts by type and location, conduit and wire by size and run type, gear by tag, and shows the sheet reference for each quantity. Quantities are separate from pricing so you can update either one. A second estimator checks counts and run lengths against the marked-up plans before pricing, and assumptions about unmarked runs, allowances and exclusions are written down.
How Bid Sharp helps with electrical estimating
Bid Sharp prepares electrical takeoffs and estimates from your drawings and specifications, with quantities traceable to marked-up plans and a second-person review. Send the electrical sheets, Division 26 specifications and addenda with your bid date. See electrical estimating, quantity takeoff services and our glossary, or send us your plans.
Have a bid coming up?
Upload your plans and bid date. We reply with scope, price and turnaround.
Frequently asked questions
What is an electrical takeoff?
+
An electrical takeoff is the measured list of devices, fixtures, conduit, wire, panels and equipment taken from the electrical drawings and specifications. The estimator then prices the quantities with material and labor costs.
Which CSI division covers electrical work?
+
Electrical work is Division 26 in CSI MasterFormat. Communications are Division 27 and electronic safety and security, such as fire alarm, are Division 28.
How do you estimate conduit and wire when runs are not drawn to scale?
+
Estimators measure the likely path from panel to device, add vertical drops and rises and an allowance for offsets and pull boxes, then group runs by conduit type, size and conductor count.
What are the most common electrical estimating mistakes?
+
Missing items in the specifications or schedules, using a fixture replaced by an addendum, forgetting equipment connections, underestimating wire on long runs and omitting temporary power or testing.
Can Bid Sharp prepare electrical estimates?
+
Yes. Bid Sharp prepares electrical takeoffs and estimates from your drawings and specifications. A second estimator reviews the work and the contractor reviews, signs and submits the bid.
Written by the Bid Sharp Estimating Team
Bid Sharp provides construction estimating, quantity takeoff, structural and permit drawings, shop drawings and scheduling for contractors across the United States. This article is general information, not legal or engineering advice.


